K Line Extension to Torrance

    Project Website
Project Notices

Field Investigation Work - Metro/BNSF Railroad & Hawthorne Bl

10/14/26

Summary

Metro is extending light rail service from the Redondo Beach (Marine) Station to the Torrance Transit Center, adding 4.7 miles of new track and two new stations. By providing a fast, frequent and reliable transit option to the South Bay, the Project will improve environmental and economic outcomes across LA County. On January 22, 2026, the Metro Board of Directors certified the Final Environmental Impact Report (FEIR) and approved the K Line Extension to Torrance Project with the Hawthorne Option as the project alignment. Starting mid-October, you might notice crews on Hawthorne Bl conducting field investigation work to support ongoing engineering and design efforts.

What

Metro's contractor will perform geotechnical and potholing investigation, and survey work to confirm existing field conditions. Field investigations may include land surveying, identifying utilities within the Project area, taking soil samples and measurements to understand conditions beneath the ground surface through potholing (or drilling small holes), traffic and roadway assessments, and other site evaluations. Most activities will be temporary and localized.

Where/When

Survey and geotechnical investigation is anticipated to start October 19, 2026 followed by potholing activities for an approximate duration of 6-months. Work hours are 7:30AM to 6:00PM Monday - Friday.

Location Limits of work area Anticipated start date and duration Traffic adjustments during work hours
Metro/BNSF railroad right-of-way From Redondo Beach Station to Inglewood Bl Starting October 19 for approximately 4 weeks No impacts to the public
City of Lawndale NB Hawthorne Bl from 165th St to 171st St As early as October 26 for approximately 9 weeks NB median parking ingress closed
1-405 Freeway, cities of Lawndale & Redondo Beach 1-405 Freeway from Inglewood Av to Hawthorne Bl As early as November 9 for approximately 8 weeks Ramp and freeway lane closures.
City of Redondo Beach SB Hawthorne Bl from Redondo Beach Bl to Artesia Bl As early as December 13 for approximately 6 weeks SB left turn pocket closed
City of Torrance NB Hawthorne Bl from 177th St to 190th St As early as January 18 for approximately 6 weeks NB left turn pocket & one lane closed at 178th & 182nd: Two lanes closed south of 186th

What to Expect

Thru traffic will be maintained on Hawthorne Bl; no more than two traffic lanes will be closed.

Did this work notice help?
Help improve how Metro shares construction updates. Take a short survey to tell us whether this notice was clear, useful, and easy to understand. | Survey