Central Av – I-710: Start of Construction
Summary: Metro has a plan to ease traffic and enhance safety on the I-105, which includes the conversion of the existing High Occupancy Vehicle (HOV) lane, or carpool lane, into two Metro ExpressLanes in each direction on the I-105. As construction progresses throughout the entire I-105 corridor, work crews anticipate the start of construction in the Segment 2 area, between Central Av and I-710, in mid-October 2026. Construction in the Segment 2 area is anticipated to be completed in 2029.
See below for a summary of upcoming work activities leading up to major construction in the Segment 2 area.
|
Construction Activities |
Construction Details |
Anticipated Schedule and Work Hours |
|
Temporary ramp pavement construction |
Work at selected on and off-ramps to support future construction. Work includes temporary restriping of the ramps and concrete barrier installation.
|
|
|
Freeway restriping, concrete barrier installation, and outside roadway grinding work |
Temporary re-striping of freeway lanes and concrete barrier installation to establish work zones along the corridor in support of long-term construction. Traffic lanes will be restriped to the existing lane configuration of one HOV lane & three general purpose lanes in each direction. |
|
|
Tree and vegetation removal |
The removal of trees and vegetation along the I-105 corridor will be performed as necessary at locations between Stanford Av to Atlantic Bl in both directions to support future construction. Upon completion of the project the landscaping will be restored with new trees and vegetation. |
|
|
Start of major construction |
Includes new sound walls and retaining walls, new roadway pavement construction, undercrossing/bridge construction (Success Av to Atlantic Bl), drainage system upgrades, and overhead sign structure installations. |
|
What to Expect
-
During construction, intermittent nighttime freeway lane reductions and ramp closures are necessary to safely perform work activities. Consecutive ramps will not be closed at the same time.
-
Most daytime work activities will be conducted within work zones behind concrete barriers and are not expected to result in closures on the freeway. Nighttime work will be conducted on an as-needed basis to perform certain work activities as required.
-
Most undercrossing/bridge construction will require either a long-term traffic reconfiguration (lane reductions) or an extended full street closure as needed at particular locations.
Noteworthy:
-
Most undercrossing/bridge construction will require either a long-term traffic reconfiguration (lane reductions) or an extended full street closure as needed at particular locations.
-
Construction is dynamic and work schedules are subject to change.
-
To receive electronic updates, please visit the project website at Metro.net/105expresslanes.
|