Clearwood Ct Geotechnical Fieldwork

Summary

Metro’s subcontractor will be performing required preliminary, limited geotechnical fieldwork to gather information on existing soil and rock conditions on Clearwood Ct west of the intersection with Nicada Dr. 

When 
  • Mid-December 2026 through January 2027
Work Hours
  • Monday – Friday, 9am-3pm
  • Work will be periodic with a cumulative duration of up to five weeks. 
Lane Closure
  • An approximate 100-foot section of the north shoulder and lane of Clearwood Ct west of the intersection with Nicada Dr will be periodically closed. This area is adjacent to the greenbelt area east of the residence at 10521 Clearwood Ct. In and out access will be maintained throughout the workspace. 

Parking Restrictions
  • There will be parking restrictions along both sides to the roadway in the vicinity of the workspace. 

More Information
Local access, Pedestrian Access, and Emergency Responder Access will be maintained during work activities.

Construction is a dynamic process, and information is subject to change without notice.

Metro Bus Service
Nearby bus stops or routes may be temporarily affected. Riders can call 323.GO.METRO or use Metro’s App for current service information and trip planning.

If you see an encampment or someone in need: Visit LAHSA's online outreach request site LA-HOP at https://www.lahsa.org/portal/apps/la-hop/request. For more information and referrals for any Health and Human Services, call 2‐1‐1 or visit 211LA.org.