Cross Passage 31 Restoration at Doheny Dr

Summary 

Construction and street restoration work for cross passages continues on Wilshire Bl. The current location on Wilshire Bl that will be undergoing street restoration is located on Wilshire Bl between Doheny Dr and Wetherly Dr. The work activity taking place includes saw cutting, roadway grinding, trenching, trench backfill, and street paving beginning Thursday, October 10th.  

Where 

On Wilshire Bl between Doheny Dr and Wetherly Dr 


When 

Date: 

  • Thursday, October 10th  

  • Anticipated duration: 3-4 weeks 


Work hours:  

  • Monday - Friday 9AM – 4PM 

Traffic Control: 

  • Wilshire Bl will be reduced to two lanes in the eastbound and westbound directions during work activity.  

  • Parking meters on the north and south side of Wilshire Bl from Doheny Dr and Wetherly Dr will be restricted during work activity.  

  • Driveway access to CVS Pharmacy at 9045 Wilshire will be maintained during work activity  

  • Bus stop locations on the north and south sidewalks at the intersection of Wilshire Bl and Doheny Dr will be maintained during work activity.   

  • Pedestrian access will be maintained during work activity.  

Noteworthy: 

  • All work has or will receive the necessary permits and approvals. 

  • Access to driveways, residences & businesses will be maintained at all times unless notified in advance. 

  • Access for pedestrians will be maintained outside of construction zones. 

  • Access for the Fire Department and emergency responders will be maintained. 

  • Parking restrictions will be implemented in the immediate area of the work zone. 

  • Construction is dynamic and schedules are subject to change. 

  • 24/7 Hotline: 213-922-6934 

Metro Access: 

Metro bus stops may be relocated, or lines could be impacted. For information about changes to Metro service, please call 323.GoMetro. Passengers are encouraged to use the Transit App to plan their travels. 

Next Community Meeting: 

  • D Line Sections 1 and 2 City of Beverly Hills. November 6, 2024, at 12pm, Virtual 

  • Zoom: https://zoom.us/j/96626476708 

  • Webinar ID: 966 2647 6708, No password required 

Metro Updates

Construction is a dynamic process and information is subject to change without notice. Visit the project website for the most up to date information.

Local access, Pedestrian Access, and Emergency Responder Access is maintained during work activities. 

Metro bus stops may be relocated or lines could be impacted. For up to date information follow us on Twitter @metrolaalerts, metro.net/advisories or call 323.GOMETRO for updates and trip planning assistance. Passengers are encouraged to use the Transit App to plan their travels. 

If you see an encampment or someone in need: Visit LAHSA's online outreach request site LA HOP at www.lahsa.org/portal/apps/la-hop/request.   

For more information and referrals for any Health and Human services, please dial 2‐1‐1, call (800) 399‐6993, or visit 211LA.org. 
Privacy Policy | Terms of Use
Copyright ©2024 Metro