Metro is making safety improvements on the Eastbound SR-91 from the Southbound I-710 to the Eastbound SR-91 connection through Atlantic Av and Cherry Av. Work on Eastbound SR-91 is designed to reduce collisions, improve vehicle merging, and help traffic move more safely in this area. Improvements include a new eastbound auxiliary lane, extended on-ramps and off-ramps, bridge widening, and replacement of existing soundwalls along the corridor.

What is an auxiliary lane?

An auxiliary lane is an additional lane provided for a short distance, usually between an on-ramp and an off-ramp, to help drivers merge in and out of traffic more safely and smoothly.

Upcoming

Construction is expected to begin in Spring 2026 and continue through 2029. The work will be completed in phases to minimize impacts and construction activity near homes and businesses. Advance notice will be shared before major construction begins.

Work Hours:

  • Monday through Friday from 7am to 7pm
  • Nightwork: 8pm to 6am, as needed
  • Saturdays 9am to 6pm, as needed
The first stage is expected to take place between the Southbound I-710 connector and Myrtle Av. The following construction activities are anticipated during stage 1: 
 
No. Construction Activities Stage 1 Construction Activity Details Stage 1 Anticipated Start Dates 
1. Traffic shifts and restriping Crews will restripe the Eastbound SR-91 for future auxiliary lane and shift temporary traffic pattern during construction. As early as mid-April 2026, (approximately 1 week)
2. Atlantic Av on-ramp and off-ramp improvements Existing soundwalls will be removed and reconstructed to accommodate the future auxiliary lane.  As early as June 2026, (approximately 6 months) 
3. Soundwall and retaining wall removal and reconstruction  Existing soundwalls will be removed and reconstructed to accommodate the future auxiliary lane. As early as January 2027, (approximately 7 months) 
4. Bridge Widening Construction will take place on the freeway bridges over Atlantic Av. Myrtle Av will be widened to accommodate the future auxiliary lane. As early as January 2027 (approximately 6 months) 

Construction is a dynamic process and work schedules are subject to change. For additional information, contact Metro Community Relations at 213.922.4091 or EB91@metro.net.
 

Metro Updates

Construction is a dynamic process and information is subject to change without notice. Visit the project website for the most up to date information.

Local access, Pedestrian Access, and Emergency Responder Access is maintained during work activities. 

Metro bus stops may be relocated or lines could be impacted. For up to date information follow us on Twitter
@metrolaalerts, metro.net/advisories or call 323.GOMETRO for updates and trip planning assistance. 

If you see an encampment or someone in need: Visit LAHSA's online outreach request site LA-HOP at https://www.lahsa.org/portal/apps/la-hop/request. For more information and referrals for any Health and Human Services, call 2‐1‐1 or visit 211LA.org.
Did this work notice help?
Help improve how Metro shares construction updates. Take a short survey to tell us whether this notice was clear, useful, and easy to understand. |
Survey

Privacy Policy | Terms of Use
Copyright ©2026 Metro