I-105 ExpressLanes Project
Back to Work Notices

Utility Work: Imperial Hwy/ Alameda St

Summary: Metro has a plan to ease traffic and enhance safety on the I-105, which includes the conversion of the existing High Occupancy Vehicle (HOV) lane, or carpool lane, into two Metro  ExpressLanes in each direction on the I-105. Early preparation work activities are soon anticipated in advance of major construction in the eastern areas of the I-105 corridor, as the western area has been under construction since 2025.   

As part of the I-105 improvements, work crews will perform early utility investigation and waterline relocation work activities along Imperial Hwy at Alameda St to support upcoming major construction. These activities are anticipated to begin in late May and will continue through late July 2026. Construction for Segment 2, between Central Av and I-710, is anticipated to start in fall 2026, while Segment 3, between I-710 and Studebaker Rd, is expected to begin construction in mid-2026. Both Segments 2 and 3 are anticipated to be completed in 2029. 

 
Location: Work crews will conduct preparatory activities along Imperial Av between Mona Bl and Philadelphia Wy involving utility investigation and waterline relocation work activities. 

Work Schedule  
  • Work is anticipated to start in late May and continue through late July 2026, lasting approximately two months. 
  • ​​​​​​​Work hours are anticipated from Monday through Friday, during daytime hours (9am to 3pm), along with intermittent nighttime work (9pm to 5am)   
What to Expect: 
  • Two phases of traffic control involving lane reductions will be implemented to safely perform this work:  
    • In the eastbound direction, two lanes will be closed, leaving one lane of traffic open. (Both phases)  
    • In the westbound direction, one lane will be closed, leaving two lanes of traffic open. (Second phase only) 
  • Work activities include trenching, excavation, water line installation, and potholing.  
  • These work activities are the beginning of long-term construction involving the widening and retrofitting of the westbound I-105 along Imperial Hwy at this location, lasting approximately 2 years. 
Noteworthy: 
  • Please note that construction is dynamic and work schedules are subject to change based on the progress of work and weather conditions.
  • For electronic project updates, please sign up under “Contact Us” at Metro.net/105expresslanes. 

Metro Updates

Construction is a dynamic process and information is subject to change without notice. Visit the project website for the most up to date information.

Local access, Pedestrian Access, and Emergency Responder Access is maintained during work activities. 

Metro bus stops may be relocated or lines could be impacted. For up to date information follow us on Twitter
@metrolaalerts, metro.net/advisories or call 323.GOMETRO for updates and trip planning assistance. 

If you see an encampment or someone in need: Visit LAHSA's online outreach request site LA-HOP at https://www.lahsa.org/portal/apps/la-hop/request. For more information and referrals for any Health and Human Services, call 2‐1‐1 or visit 211LA.org.
Did this work notice help?
Help improve how Metro shares construction updates. Take a short survey to tell us whether this notice was clear, useful, and easy to understand. |
Survey

Privacy Policy | Terms of Use
Copyright ©2026 Metro