24-inch Waterline Installation
SummaryThe contractor is preparing to install a 24-inch water line on Crenshaw Blvd between King Blvd and Stocker St as a part of the final construction activities for the Crenshaw LAX Punch Out Work Project
WhatSawcut as necessary, pothole existing utilities, demo existing asphalt, in trench, excavate, install waterline and accessories.
WhereOn Crenshaw Bl between MLK Blvd and Stocker St.
When
-
Beginning as early as July 19, 2024, for approximately three months.
-
Monday to Friday 7am to 4pm, night work as needed, weather permitting.
What to Expect
-
Crenshaw Blvd and Vernon Ave NB Lane 3, closure, RTP turning EB onto to Vernon Ave -
Crenshaw Blvd NB (between Vernon Ave and 43rd Pl) lane 3 and lane 2 closure off of Vernon into Crenshaw -
WB Vernon Ave RTP turning onto NB Crenshaw Blvd closure -
Crenshaw Blvd NB(between 43rd Pl & 43rd st) lane 3,2 closure -
Crenshaw Blvd NB (between 43rd St and Stocker St) lane1,2 & 3 and left turning pocket 1 on to EB Stocker St closure -
Noise and dust control measures will be in place to minimize impacts. -
Construction night work, if needed, will be minimized and within allowable noise levels.
Noteworthy
-
All work will receive necessary permits and approvals from the City of Los Angeles before starting work.
-
Access for emergency vehicles will be maintained.
-
Pedestrian access will be maintained outside the work area.
-
Access to business/residential driveways within the work zone will be maintained.
-
Construction is a dynamic process, and information is subject to change without notice.
|