Back to Active Notices     Back to Project Page
N Beverly Glen/Perdido Ln Geotechnical Fieldwork

Summary

Metro’s subcontractor will be performing required preliminary, limited geotechnical fieldwork to gather information on existing soil and rock conditions on N Beverly Glen Bl near the intersection with Perdido Ln. 

When 
  • Late October to December 2026
Work Hours
  • Monday – Friday, 9am-3:30pm, Saturday, 8am-6pm
  • Work will be periodic with a cumulative duration of up to four weeks. 
Parking Restrictions
  • There will be periodic lane closures of portions of the southbound lane of Beverly Glen Bl from the intersection with Perdido Ln to approximately 200 feet to the south.
Traffic Control
  • At the intersection of Beverly Glen Bl and Perdido Ln, flaggers will be in place to allow traffic around the closure in one direction at a time.

More Information
Local access, Pedestrian Access, and Emergency Responder Access will be maintained during work activities.

Construction is a dynamic process, and information is subject to change without notice.

Metro Bus Service
Nearby bus stops or routes may be temporarily affected. Riders can call 323.GO.METRO or use Metro’s App for current service information and trip planning.

If you see an encampment or someone in need: Visit LAHSA's online outreach request site LA-HOP at https://www.lahsa.org/portal/apps/la-hop/request. For more information and referrals for any Health and Human Services, call 2‐1‐1 or visit 211LA.org.

Privacy Policy | Terms of Use
Copyright ©2026 Metro