Santa Clara Overhead Bridge ConstructionSummaryAs part of the I-5 North County Enhancements Project, Metro’s contractor OHLA-USA, will be extending the existing Santa Clara Overhead Bridge, located between Magic Mountain Pkwy and Rye Canyon Rd, to accommodate the new high-occupancy vehicle (HOV) lanes along the I-5 corridor. Construction will take place along the outside shoulders, and along Santa Clara Overhead Bridge adjacent to the I-5. Activities will include excavation, shoring, pile driving, form, rebar, concrete, soil backfill, falsework installation and removal, and electrical work on the bike path. Construction activities along northbound and southbound I-5 are anticipated to be completed by December 2024. What to Expect & Traffic Control
Essential Details
Noteworthy
Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing of
|