Southeast Gateway Line

 Project Website 
Project Notices

Utility Investigation: November 17, 2025 - December 2025 

Summary  

Metro’s contractor, C Below, Inc., will be conducting underground utility investigations along the project alignment in the Cities of Vernon, Huntington Park and Bell in preparation for future engineering design of the Southeast Gateway Line. The work will include an excavation process to locate underground utility lines. 

Work Hours, Dates and Locations (weather permitting, excluding holidays) 

  • Work Hours:
    • Cities of Huntington Park and Bell: 7:00 am – 4:00 pm, Monday through Friday 
    • City of Vernon: 8:00 am – 4:00 pm, Monday through Friday 
  • Schedule: As early as November 19, 2025 through December 2025 

  • Locations: 
    • Randolph St at Pacific Bl to State St/Boyle Av 
    • Salt Lake Av and Gage Av
    • Salt Lake Av and Bell Av 
    • Salt Lake Av and Florence Av
    • Salt Lake Av and Walnut St 
    • Salt Lake Av and Live Oak St 
    • Salt Lake Av and Clara St 
    • Salt Lake Av and Hill St 
    • Salt Lake Av and Otis Av
    • Salt Lake Av and Santa Ana St 
    • Randolph St and Hood Av  
    • Randolph St and Newell St 

What to Expect 

  • Short-term traffic impacts. 

  • Lane reductions or closures on streets during work hours. Lanes will be restored daily upon work completion. 

  • Signage will be posted to guide vehicles around work zones. 

  • Equipment in the street, excavations, and surface conditions will be restored (e.g., patching roads and pavement) after drilling is completed.  

Noteworthy 

  • All work has received necessary permits and approvals. 

  • Access to emergency responders will be maintained during construction. 

  • Access to private driveways, residences, and businesses, will always be maintained unless notified in advance. 

  • Construction is a dynamic process and work schedules and timelines are subject to change. 

If you see an encampment or someone in need: Visit LAHSA's online outreach request site LA-HOP at www.lahsa.org/portal/apps/la-hop/request. For more information and referrals for any Health and Human Services, call 2‐1‐1 or visit 211LA.org.     

 



Resumen 

El contratista de Metro, C Below, Inc., realizará investigaciones de servicios públicos subterráneos en las ciudades de Vernon, Huntington Park y Bell, como preparación para el diseño de ingeniería futura de la Línea de Southeast Gateway. El trabajo incluirá un proceso de excavación para localizar las líneas de servicios públicos subterráneos. . 

Horario, Fechas y Ubicaciones de Trabajo (si el clima lo permite, excluyendo los días festivos) 

  • Horario de trabajo: 
    • Ciudades de Huntington Park y Bell: 7:00 am a 4:00 pm, de lunes a viernes 
    • Ciudad de Vernon: 8:00 a 4:00 pm, de lunes a viernes 
  • Fechas programadas: desde el 17 de noviembre de 2025 hasta diciembre de 2025 

  • Ubicaciones:

    • Randolph St at Pacific Bl to State St/Boyle Av 
    • Salt Lake Av and Gage Av
    • Salt Lake Av and Bell Av 
    • Salt Lake Av and Florence Av
    • Salt Lake Av and Walnut St 
    • Salt Lake Av and Live Oak St 
    • Salt Lake Av and Clara St 
    • Salt Lake Av and Hill St 
    • Salt Lake Av and Otis Av
    • Salt Lake Av and Santa Ana St 
    • Randolph St and Hood Av  
    • Randolph St and Newell St 

Qué Puedes Esperar 

  • Impactos temporales al tráfico. 

  • Reducción o cierre de carriles en las calles durante el horario de trabajo. Los carriles se reabrirán diariamente al terminar las labores. 

  • Se colocarán señalamientos para guiar a los vehículos alrededor de las zonas de trabajo. 

  • Después de concluir la excavación, se retirará el equipo de la calle y se restaurará la superficie (por ejemplo, parchado de calles y pavimento). 

Notable 

  • Todas las actividades de construcción han recibido los permisos y aprobaciones necesarias. 

  • Se mantendrá el acceso a los servicios de emergencia durante la construcción. 

  • Acceso a entradas de coche privadas, residencias, y negocios van a mantenerse accesibles a menos que haya notificación previa. 

  • Las operaciones de construcción son dinámicas y los horarios y plazos de trabajo están sujetos a cambios. 

Si ve campamento o alguien necesitado: Visite el sitio de solicitud de alcance en línea de LAHSA LA-HOP en www.lahsa.org/portal/apps/la-hop/request. Para obtener más información y referencias para cualquier servicio de salud y humanos, marque 2‐1‐1 o visite 211LA.org.  

Metro Updates

Construction is a dynamic process and information is subject to change without notice, visit the project website for the most up to date information.

Local access, Pedestrian Access, and Emergency Responder Access is maintained during work activities. 

Metro bus stops may be relocated or lines could be impacted. For up to date information follow us on Twitter @metrolaalerts, metro.net/advisories or call 323.GOMETRO for updates and trip planning assistance. Passengers are encouraged to use the Transit App to plan their travels. 

If you see an encampment or someone in need: Visit LAHSA's online outreach request site LA HOP at www.lahsa.org/portal/apps/la-hop/request.   

For more information and referrals for any Health and Human services, please dial 2‐1‐1, call (800) 399‐6993, or visit 211LA.org. 

Privacy Policy | Terms of Use
Copyright ©2025 Metro