Southeast Gateway Line

    Project Website
Project Notices

Utility Field Investigations

Summary
Metro’s contractor, C Below, Inc., will be conducting underground utility investigations along the project alignment in the City of Huntington Park, Cudahy and South Gate in preparation for future engineering design of the Southeast Gateway Line. The work will include an excavation process to locate underground utility lines.
                         
Schedule (weather permitting, excluding holidays)

  • April 30 through July 31, 2026
  • Work hours: Monday through Friday, 8:30am to 5:30pm.
  • Intermittent weekend work and night work may be necessary.
Locations: 
  • City of Huntington Park
    • Salt Lake Av
    • Florence Av
    • Santa Ana St
       
  • City of Cudahy
    • Salt Lake Ave/Otis Av
    • Ardine St
       
  • City of South Gate 
    • Ardine St and Salt Lake Av
    • Atlantic Av and Patata St
    • Century Bl and Center St
    • Firestone Pl and Firestone Bl 
    • Gardendale St and Dakota Av
    • Imperial Hwy and Garfield Pl
    • Main St and Dakota Av
    • Neville Av and Mason St
    • Rayo Av and Firestone Bl
    • Santa Ana St and Salt Lake Av
    • Southern Av and Salt Lake Av
What to Expect
  • Lane reductions or closures on streets during work hours. Lanes will be restored daily upon work completion.
  • Signage will be posted to guide vehicles around work zones.
  • Equipment in the street, excavations, and surface conditions will be restored after drilling is completed.
Noteworthy
  • All work has received necessary permits and approvals. 
  • Access to emergency responders will be maintained during construction. 
  • Access to private driveways, residences, and businesses, will always be maintained unless notified in advance. 
  • Construction is a dynamic process and work schedules and timelines are subject to change.

Metro Updates

Construction is a dynamic process and information is subject to change without notice, visit the project website for the most up to date information.

Local access, Pedestrian Access, and Emergency Responder Access is maintained during work activities. 

Metro bus stops may be relocated or lines could be impacted. For up to date information follow us on Twitter @metrolaalerts, metro.net/advisories or call 323.GOMETRO for updates and trip planning assistance. Passengers are encouraged to use the Transit App to plan their travels. 

If you see an encampment or someone in need: Visit LAHSA's online outreach request site LA HOP at www.lahsa.org/portal/apps/la-hop/request.   

For more information and referrals for any Health and Human services, please dial 2‐1‐1, call (800) 399‐6993, or visit 211LA.org. 
Did this work notice help?
Help improve how Metro shares construction updates. Take a short survey to tell us whether this notice was clear, useful, and easy to understand. | Survey

Privacy Policy | Terms of Use
Copyright ©2026 Metro