Century City Station – Monthly Look-Ahead: May 2026 

This monthly notification is an outline of construction activities in Century City for the month of May 2026.  
All work has received necessary permits and approvals or is pending approval. Dates are subject to change. Additional notices detailing these activities are sent by email through the D Line Extension, Section 2 database. To be added to the D Line stakeholder list for construction updates, please email us at metrodline@metro.net.  
 
Upcoming Deck Removal: COMPLETED

  • The contractor has been working on deck panel removal and street restoration along Constellation Bl from Century Park East to just west of Avenue of the Stars. This work will be completed in four sequential phases, each lasting 14 days, with traffic control implemented to progress linearly from east to west. Upon completion of deck removal, traffic control will be reestablished on Constellation Bl to support ongoing construction activities. 
  • Phase 4 began on Thursday April 23rd and is anticipated to end on Sunday May 10th.  
  • During Phase 4 work activities, Constellation Bl will be closed between Avenue of the Stars and Solar Way.  
  • Further traffic control information will be provided through construction notices and direct stakeholder outreach. 
  • Construction is dynamic and dates are subject to change.   
Side Structure/Appendage Work Activity
  • Work will continue behind k-rail enclosures to construct appendages along the future station within the current traffic closures and will continue following the completion of the deck removal activities.  
  • Construction occurs within current traffic closures around the station area to accommodate this work and the contractor will implement additional traffic phasing after deck removal to continue work on the remaining structures. 
  • The contractor will be performing potholing activities for appendage piles, which will require temporary sidewalk closures and single-lane traffic operations with flagging in place for both westbound and eastbound traffic on Constellation Bl.  
Station Construction and Concrete Placement Completion
  • Placement of structural concrete for the Constellation Station is complete.
  • Construction of the interior and above roof structures will be ongoing underground beneath Constellation Bl. This work takes place 24 hours a day Monday through Saturday.
Station Backfill Operations Progress
  • The contractor is continuing to conduct backfill operations for the future station above the final concrete structure in the month of May.
  • The backfill operation will require daily intermittent nighttime closures coordinated with the concrete placement.
Work within Construction Staging Yards (day work and weekend nights)
  • Ongoing construction continues within the sound walls at the staging yards located at 1940, 1950, 2010 and 2040 Century Park East.
Northbound Solar Way Closure: COMPLETED
  • The contractor will implement a closure of the northbound lane on Solar Way to support crane demobilization activity.  
  • This is a lane closure only and no work will take place in the northbound Solar Way lane.   
  • Anticipated work duration Friday, May 1st at 8PM through Monday, May 4th at 6AM. Work will take place 24 hours a day.  
Avenue of the Stars Utility Work Northbound Lane Closure: COMPLETED
  • The contractor will implement a full closure of north bound Avenue of the Stars at Constellation Bl to just north of the intersection. 
  • This work is needed to support ongoing utility work activity with an anticipated duration of Tuesday, April 28th through Friday, May 8th. Work hours will be 8PM-6AM. 
Noteworthy:
  • The JMB Project construction located on the NE corner of Constellation and Avenue of the Stars is immediately adjacent to the Metro D Line Subway construction. For information regarding JMB construction, please contact Bonnie Christopher at 310-843-4022 (direct) or 310-551-007 (office).
Next Community Meeting 
  • D Line – Beverly Hills Stations, May 13, 2026, at 12pm, Virtual 
  • Link: https://us02web.zoom.us/j/82203486209 Webinar ID: 822 0348 6209 

Metro Updates

Construction is a dynamic process and information is subject to change without notice. Visit the project website for the most up to date information.

Local access, Pedestrian Access, and Emergency Responder Access is maintained during work activities. 

Metro bus stops may be relocated or lines could be impacted. For up to date information follow us on Twitter @metrolaalerts, metro.net/advisories or call 323.GOMETRO for updates and trip planning assistance. 

If you see an encampment or someone in need: Visit LAHSA's online outreach request site LA-HOP at https://www.lahsa.org/portal/apps/la-hop/request. For more information and referrals for any Health and Human Services, call 2‐1‐1 or visit 211LA.org.
Did this work notice help?
Help improve how Metro shares construction updates. Take a short survey to tell us whether this notice was clear, useful, and easy to understand. | Survey
Privacy Policy | Terms of Use
Copyright ©2026 Metro