Summary 

Lane closures will be enforced on Constellation Bl and Avenue of the Stars for pile installation. Work will be done in two phases from August 3 to 20.

Phase 1 

  • Monday, August 3 – Wednesday, August 5
  • 9pm - 5am

Traffic Control

  • Eastbound Constellation Bl will be closed between Solar Way and Avenue of the Stars.  
  • Access to the Fairmont Hotel parking garage will be maintained from the west via Century Park West.  
  • The south sidewalk on Constellation Bl between Solar Way and Avenue of the Stars will be closed. Pedestrians will be detoured around the work area using the designated temporary pedestrian route.  
  • Flaggers will assist with pedestrian crossings and direct vehicular traffic safely during construction activities.  
Phase 2 
  • Thursday, August 6 – Thursday, August 20
  • 9pm - 5am
Traffic Control
  • Eastbound Constellation Bl will be closed between the Fairmont Hotel driveway and Avenue of the Stars. 
  • Southbound Avenue of the Stars will be closed from the south side crosswalk to the Fairmont Valet driveway on Avenue of the Stars. 
  • Northbound Avenue of the Stars will remain open to the Fairmont Hotel driveway to maintain access to the hotel and adjacent properties.  
  • A U-turn will be implemented for southbound traffic at the Avenue of the Stars and Constellation intersection for vehicles that need access to 1900 and 1800 Avenue of the Stars.  
  • Temporary lane closures will be implemented on Constellation Bl and Avenue of the Stars to accommodate pile installation activities.  
  • Flaggers will direct pedestrian crossings and vehicular traffic safely during construction activities.
Noteworthy
  • All work has received the necessary permits and approvals. 
  • Access to driveways, residences & businesses will be maintained at all times unless notified in advance. 
  • Access for pedestrians will be maintained outside of construction zones. 
  • Access for the Fire Department and emergency responders will be maintained. 
  • Parking restrictions will be implemented in the immediate area of the work zone. 
  • Construction is dynamic and schedules are subject to change. 
  • 24/7 Hotline: 213-922-6934 

Metro Updates

Construction is a dynamic process and information is subject to change without notice. Visit the project website for the most up to date information.

Local access, Pedestrian Access, and Emergency Responder Access is maintained during work activities. 

Metro bus stops may be relocated or lines could be impacted. For up to date information follow us on Twitter @metrolaalerts, metro.net/advisories or call 323.GOMETRO for updates and trip planning assistance. 

If you see an encampment or someone in need: Visit LAHSA's online outreach request site LA-HOP at https://www.lahsa.org/portal/apps/la-hop/request. For more information and referrals for any Health and Human Services, call 2‐1‐1 or visit 211LA.org.
Did this work notice help?
Help improve how Metro shares construction updates. Take a short survey to tell us whether this notice was clear, useful, and easy to understand. | Survey
Privacy Policy | Terms of Use
Copyright ©2026 Metro