Decommissioning of Geotechnical Instruments between Beverly Dr and Linden Dr

Summary 

The contractor will be implementing traffic lane and sidewalk closures to support the removal of geotechnical instruments across multiple locations along the project alignment. This phase of instrumentation removal will be conducted on weekday evenings between Beverly Dr and Linden Dr.

When: 

  • Weekdays: Monday-Friday
  • Nighttime work hours: 8:15PM-7AM

Date/Location/Traffic Co

  • September 9-11 Location 1: Wilshire Bl between Bedford Dr and Roxbury Dr
    • Westbound Wilshire Bl will be reduced to one lane between Bedford Dr and Roxbury Dr.
    • Access to the alley between N Bedford Dr and Camden Dr will remain accessible.
    • Southbound Brighton Wy will be reduced to one lane at Wilshire Bl.
  • September 9-11 - Location 2: Wilshire Bl between Camden Dr and Brighton Wy 
    • Westbound Wilshire Bl will be reduced to one lane between Camden Dr and Brighton Wy
  • September 9-11 - Location 3: Wilshire Bl between Peck Dr and Bedford Dr
    • Westbound Wilshire Bl will be reduced to two lanes between Peck Dr and Bedford Dr
  • September 9-11 - Location 4: Wilshire Bl between Bedford Dr and Camden Dr
    • Eastbound Wilshire Bl will be reduced to one lane between Bedford Dr and Camden D
    • Southbound Bedford Dr will be reduced to two lanes at Wilshire Bl
  • September 9-11 - Location 5: Wilshire Bl between S Santa Monica Bl and just east of Linden Dr
    • Eastbound Wilshire Bl will be reduced to one lane between S Santa Monica Bl and just east of Linden Dr
    • Northbound S Linden Dr right turn lane closed at Wilshire Bl
  • Tentatively September 15-19 Location 6: Wilshire Bl between Beverly Dr and just west of Camden Dr
    • ​​​​​​​Westbound Wilshire Bl reduced to one lane between Beverly Dr and Camden Dr
    • Left turn may be restricted from westbound Wilshire Bl to Camden Dr
    • Right turn may be restricted from southbound Rodeo Dr to Wilshire Bl
    • Left turn from westbound Wilshire Bl to Dayton Wy maintained

Noteworthy: 

  • All work has or will receive the necessary permits and approvals. 

  • Access to driveways, residences & businesses will be maintained at all times unless notified in advance. 

  • Access for pedestrians will be maintained outside of construction zones. 

  • Access for the Fire Department and emergency responders will be maintained 

  • Parking restrictions will be implemented in the immediate area of the work zone. 

  • Construction is dynamic and schedules are subject to change. 24/7 Hotline: 213-922-6934 

Metro Access: 

Metro bus stops may be relocated, or lines could be impacted. For information about changes to Metro service, please call 323.GoMetro.

Next Community Meeting: 

  • D Line Sections 1, 2, & 3 October 8, 2025, at 12pm, Virtual

  • Zoom: https://zoom.us/j/96626476708 Webinar ID: 966 2647 6708 No password required

Metro Updates

Construction is a dynamic process and information is subject to change without notice. Visit the project website for the most up to date information.

Local access, Pedestrian Access, and Emergency Responder Access is maintained during work activities. 

Metro bus stops may be relocated or lines could be impacted. For up to date information follow us on Twitter @metrolaalerts, metro.net/advisories or call 323.GOMETRO for updates and trip planning assistance. 

If you see an encampment or someone in need: Visit LAHSA's online outreach request site LA-HOP at https://www.lahsa.org/portal/apps/la-hop/request. For more information and referrals for any Health and Human Services, call 2‐1‐1 or visit 211LA.org.
Privacy Policy | Terms of Use
Copyright ©2025 Metro