Wilshire Bl South Sidewalk Work Between S Canon Dr and Reeves Dr

Summary 

Sidewalk restoration continues on Wilshire Bl. Work will be done on the curb, gutter, and for underground electrical along the south side of Wilshire Bl between S Canon Dr to Reeves Dr. Work is scheduled from April 27 through June 26, 2026. 

Sidewalk closures will be implemented around the work zones. Pedestrian access to 9420 Wilshire Bl will be maintained behind K-rail safety barriers adjacent to the existing sidewalk.  

Where 

  • South sidewalk along Willshire Bl between S Crescent Dr and Reeves Dr.   

When 

  • Anticipated Start Date: Monday, April 27 
  • Anticipated Completion Date: Friday, June 26 

Work hours:  

  • Mon-Fri: 7am-4:30pm (Permitted noisy activities performed from 9am-4:30pm) 
  • Mon-Fri: 8pm-4:30am 

What to Expect:

  • Minimum 5-foot pedestrian access will be maintained through a protected K-rail pathway adjacent to the existing sidewalk. 
  • Access to 9420 Wilshire, parking lot, and existing ADA ramp will be maintained during construction. 
  • Wayfinding signage will be installed to direct visitors and pedestrians along the south side of Wilshire Bl and to 9420 Wilshire throughout construction. 

Traffic Control: 

  • Traffic control devices, including signage and K-rail barriers, will be installed as needed around the work zone. 

Noteworthy: 

  • All work has or will receive the necessary permits and approvals. 
  • Access to driveways, residences & businesses will be maintained at all times unless notified in advance. 
  • Access for pedestrians will be maintained outside of construction zones. 
  • Access for the Fire Department and emergency responders will be maintained. 
  • Parking restrictions will be implemented in the immediate area of the work zone. 
  • Construction is dynamic and schedules are subject to change.  
  • 24/7 Metro Hotline: 213-922-6934 

Metro Access:

  • Metro bus stops may be relocated, or lines could be impacted. For information about changes to Metro service, please call 323.GoMetro. 

Next Community Meeting 

  • D Line – Beverly Hills Stations, May 13, 2026, at 12pm, Virtual Link: https://us02web.zoom.us/j/82203486209 Webinar ID: 822 0348 6209 

Metro Updates

Construction is a dynamic process and information is subject to change without notice. Visit the project website for the most up to date information.

Local access, Pedestrian Access, and Emergency Responder Access is maintained during work activities. 

Metro bus stops may be relocated or lines could be impacted. For up to date information follow us on Twitter @metrolaalerts, metro.net/advisories or call 323.GOMETRO for updates and trip planning assistance. 

If you see an encampment or someone in need: Visit LAHSA's online outreach request site LA-HOP at https://www.lahsa.org/portal/apps/la-hop/request. For more information and referrals for any Health and Human Services, call 2‐1‐1 or visit 211LA.org.
Did this work notice help?
Help improve how Metro shares construction updates. Take a short survey to tell us whether this notice was clear, useful, and easy to understand. | Survey
Privacy Policy | Terms of Use
Copyright ©2026 Metro