Westwood/VA Hospital Station Excavation and Construction 

Summary  

Workers continue constructing the Westwood/VA Hospital Station within Lot 42 and the staging yard west of Bonsall Av. 

Concrete operations continue for station interior walls and roof. Current work includes steel bracing removal, waterproofing, hoisting of reinforcing steel and mechanical, electrical and plumbing (MEP) equipment. Work also includes concrete pours for exterior walls and roof slabs. Backfill operations will commence with material hauling after roof elements have cured. 

Date 

  • Through Spring 2026 

Work Hours 

  • Weekdays and Weekends 
  • 5am to 5pm 
  • 5pm to 3 am (Swing) 
  • 7pm to 5am (Electrical) 

Hauling Daytime Hours 

  • 5am to 5pm 
  • 9am to 3pm (Bonsall Av only) 
  • Hauling hours are subject to chance. If the hours do change, an updated notification with the new times will be provided. 

Traffic Control 

  • There are no traffic impacts from work in the yard. 
  • Trucks will continue to use the driveways on Bonsall Av and Wilshire Bl. 
  • The 405 freeway on and off ramps to eastbound Wilshire Bl will close at night intermittently for concrete placement.

Noteworthy 

  • All work has received necessary permits and approvals. 
  • Access for pedestrians will be maintained outside of construction zones. 
  • Access for the fire department and emergency responders will be maintained. 
  • Parking restrictions will be implemented in the immediate area of the work zone. 
  • Construction is dynamic and schedules are subject to change. 
  • 24/7 Hotline: 213-922-6934 

Metro Access 

Metro bus stops may be relocated, or lines could be impacted. For more information on changes to Metro service, please call 323.GoMetro, or visit metro.net/triplanner 

Unhoused Persons 

Metro Construction Relations staff will notify and coordinate with the appropriate Los Angeles City Council District when a person experiencing homelessness is identified on City property (e.g., streets and sidewalks) near a Metro construction site. 

  • For more information and referrals for all health and human services, please dial 2‐1‐1, call (800) 399‐6993, or visit 211LA.org. The 2‐1‐1 phone line is open 24 hours, 7 days a week.  
    If you see an encampment or someone in need: Visit LAHSA's online outreach request site LA HOP at www.lahsa.org/portal/apps/la-hop/request. 

Metro Updates

Construction is a dynamic process and information is subject to change without notice. Visit the project website for the most up to date information.

Local access, Pedestrian Access, and Emergency Responder Access is maintained during work activities. 

Metro bus stops may be relocated or lines could be impacted. For up to date information follow us on Twitter @metrolaalerts, metro.net/advisories or call 323.GOMETRO for updates and trip planning assistance. 

If you see an encampment or someone in need: Visit LAHSA's online outreach request site LA-HOP at https://www.lahsa.org/portal/apps/la-hop/request. For more information and referrals for any Health and Human Services, call 2‐1‐1 or visit 211LA.org.
Privacy Policy | Terms of Use
Copyright ©2025 Metro