Cross Passage 36 Street Restoration Work 

Summary 

The contractor will perform demolition, curb, gutter, underground electrical, and sidewalk restoration work along the south side of Wilshire Bl from S Reeves Dr to S Beverly Dr and along the east side of S Beverly Dr from Wilshire Bl to the alley. Construction activities on Wilshire Bl are scheduled to begin on Tuesday May 5, 2026, with work on S Beverly Dr scheduled to begin on Monday, May 18, 2026. All work is anticipated to be completed by June 26, 2026.  

Where

  • South sidewalk along Willshire Bl between S Reeves Dr and S Beverly Dr.   
  • East sidewalk along S Beverly Dr between Wilshire Bl and the alley.  

When

  • Anticipated Wilshire Bl Start Date: Tuesday, May 5th   
  • Anticipated S Beverly Dr Start Date: Monday, May 18th  
  • Anticipated Completion Date: Friday, June 26th   

What to Expect

  • Sidewalk will be closed. 
  • Pedestrian access along Wilshire Bl and to 9454 Wilshire will be maintained via a protected pedestrian walkway behind K-rail adjacent to the existing sidewalk.  
  • ​​​​​​​S Beverly Dr pedestrian access and to 9454 Wilshire will be maintained via ADA compliant walkways during working activity. 

Work Hours

  • Daytime Work Hours: 7AM-4:30PM (Permitted noisy activities performed from 9AM-4:30PM) 
  • ​​​​​​​Nighttime Work Hours: 8PM-4:30AM  

Traffic Control

  • Minimum 5-foot pedestrian access will be maintained through a protected K-rail pathway adjacent to the existing sidewalk and ADA compliant walkways. 
  • Access to 9454 Wilshire building will be maintained during work activity  
  • Traffic control devices, including signage and K-rail barriers, will be installed as needed around the work zone. 
  • Wayfinding signage will be installed to direct visitors and pedestrians along the south side of Wilshire Blvd and to 9454 Wilshire. 

Metro Access

  • Metro bus stops may be relocated, or lines could be impacted. Please call 323.GoMetro for details.

Noteworthy  

  • All work has received necessary permits and approvals. 
  • Access for pedestrians will be maintained outside of the construction zone. 
  • Access for emergency responders will be maintained. 
  • Construction is a dynamic process and the schedule is subject to change. 
  • 24/7 Hotline: 213-922-6934 

Next Community Meeting: 

  • D Line - Beverly Hills Stations​, May 13, 2026, at 12pm, Virtual 
  • Link: https://us02web.zoom.us/j/82203486209 Webinar ID: 822 0348 6209  

Metro Updates

Construction is a dynamic process and information is subject to change without notice. Visit the project website for the most up to date information.

Local access, Pedestrian Access, and Emergency Responder Access is maintained during work activities. 

Metro bus stops may be relocated or lines could be impacted. For up to date information follow us on Twitter @metrolaalerts, metro.net/advisories or call 323.GOMETRO for updates and trip planning assistance. 

If you see an encampment or someone in need: Visit LAHSA's online outreach request site LA-HOP at https://www.lahsa.org/portal/apps/la-hop/request. For more information and referrals for any Health and Human Services, call 2‐1‐1 or visit 211LA.org.
Did this work notice help?
Help improve how Metro shares construction updates. Take a short survey to tell us whether this notice was clear, useful, and easy to understand. | Survey
Privacy Policy | Terms of Use
Copyright ©2026 Metro