Wilshire/Rodeo Deck Removal Work 2025

Summary 

The contractor will begin deck removal and street restoration work for the future Wilshire/Rodeo Station in March 2025. To expedite construction, the City of Beverly Hills has approved an alternative closure plan proposed by the contractor and Metro. The plan calls for a three-week full closure instead of the 18-weekend closure originally outlined in the Memorandum of Agreement between Metro and the City of Beverly Hills.  

Wilshire Bl will be fully closed for three consecutive weeks between Crescent Dr and just east of El Camino Dr. This closure is necessary to complete deck removal, street restoration, and water service line restoration. 

Public notices with additional information will be updated and distributed prior to the full closure of Wilshire Bl. 

When 

  • Start date: March 17, 2025
  • Duration: 3 full weeks
  • Note: No work or road closures will occur during Holidays or regional events.

Traffic Control

  • Wilshire Bl will be closed between west of Crescent Dr to just east of El Camino Dr.  

  • Pedestrian access will be maintained along Wilshire Bl.   

  • Pedestrian access will be maintained along S Canon Dr and Beverly Dr. 

  • Pedestrian access will be maintained along S Reeves Dr. 

  • All commercial property driveways adjacent to the closure will be accessible. 

  • Bus stop locations along Wilshire Bl will be relocated and further information will be provided.  

Wilshire Full Closure Detour Map
Noteworthy
  • All work will receive necessary permits and approvals from the City of Beverly Hills prior to the start of work. 

  • For urgent construction-related matters needing immediate attention, please call the Metro 24/7 Hotline at 213.922.6934 or City of Beverly Hills Customer Service at 310.285.2467. 

  • Construction is a dynamic process, and information is subject to change without notice. 

  • Access for pedestrians, the Fire Dept, and emergencies will be maintained outside the construction zone.  

  • An approved detour map will be published prior to the start of the first full closure.  

Metro Updates

Construction is a dynamic process and information is subject to change without notice. Visit the project website for the most up to date information.

Local access, Pedestrian Access, and Emergency Responder Access is maintained during work activities. 

Metro bus stops may be relocated or lines could be impacted. For up to date information follow us on Twitter @metrolaalerts, metro.net/advisories or call 323.GOMETRO for updates and trip planning assistance. Passengers are encouraged to use the Transit App to plan their travels. 

If you see an encampment or someone in need: Visit LAHSA's online outreach request site LA-HOP at https://www.lahsa.org/portal/apps/la-hop/request. For more information and referrals for any Health and Human Services, call 2‐1‐1 or visit 211LA.org.
Privacy Policy | Terms of Use
Copyright ©2025 Metro